The short answer. Biosolids are the solids left over when sewage is treated. Today the City’s own plant team trucks them from its three water reclamation plants (Coffs Harbour, Woolgoolga and Moonee) to what the business paper calls the Biomass waste facility. Item 15.18 in the paper for the 26 November Ordinary Council meeting says: The expected closure of this facility in March 2027 requires a replacement treatment, reuse or disposal pathway. The City called tenders for that pathway through TenderLink and, the report says, No tenders were received. (page 1498).A

Exhibit A · from the source

The business paper's background to item 15.18 saying biosolids now go to the Biomass waste facility, which is expected to close in March 2027
Page 1498 of the business paper for the City of Coffs Harbour’s Ordinary Council Meeting of 26 November 2026, item 15.18, under the heading “Background”, read 21 November 2026. Outlined: the current haulage to the Biomass waste facility and its expected closure in March 2027. Open the item Back to the story

Three contracts, one deadline

15.16 Food and garden organics (FOGO)Receive, haul and process kerbside FOGO and self-hauled garden organics; award recommended in a confidential attachment2 tenders
15.17 Digestor and ancillary worksTreatment works at the Coffs Harbour Water Reclamation Plant; two alternative proposals, neither conforming0 conforming
15.18 Biosolids disposal 2027 to 2029Collect, load, transport and reuse or lawfully dispose of biosolids from all three plants0 tenders
City of Coffs Harbour, Ordinary Council Meeting 26 November 2026, items 15.16 (business paper pages 1493 and 1494), 15.17 (pages 1495 to 1497) and 15.18 (pages 1498 and 1499).

What the facility does now

The organics report, item 15.16, says the City’s current arrangements for processing food and garden organics sit under Contract 0304-147-TS, which it calls the Biomass Contract (page 1493). The City’s 2025/26 financial statements, attached to the annual report on the same agenda (item 15.1), name the operator of the Coffs Coast Resource Recovery Facility as Biomass Solutions (Coffs Harbour) Pty Ltd, a company that runs it under contract to the City (page 238). The paper does not say why the facility is expected to close, and we do not suggest any fault by anyone.

The same financial statements note one more pressure on the waste system. The City’s only operating landfill is the England’s Road Waste Management Facility, and At current landfilling rates we estimate that the landfill may require rehabilitation by 2026/27 Financial Year. (page 238).

Organics: two bids, a price nobody outside can see

The FOGO contract (CON00755) covers kerbside food and garden organics and the garden organics that people drop at the transfer facility at 31 Englands Road, North Boambee Valley. It runs in two phases: continuity while the Biomass Contract winds down, then the ongoing service once the incumbent has departed. The initial term starts on 6 March 2027 and runs two years and four months, with an optional one-year extension (page 1493). Tenders opened on 25 September and closed on 21 October 2026. Two came in, from Soilco Operations Qld Pty Ltd and Australian Native Landscapes Pty Ltd (page 1494). Which one staff recommend, and at what price, is in a confidential attachment; the public report says only that tenders were within the pre-tender estimate. The recommendation also asks councillors to keep point 5 of their resolution confidential.

Treatment: one unpriced idea, one non-response

The digestor contract (CON00824) was meant to cover the digestor process, power and control works, biosolids storage and loadout, waterproofing the digestor tank and new surface aerators at the Coffs Harbour plant. Tender documents allowed alternative and non-conforming bids. None conformed (page 1495).

Pyrocal Pty Ltd of Wellcamp, Queensland, proposed drying and heating biosolids in a low-oxygen environment to make biochar, but the report says it did not provide tender schedules, scope or pricing, so the bid could not be evaluated (page 1496).

The other is the more striking. Ventia Australia Pty Ltd of North Sydney, with Reduce Solutions Pty Ltd, which the report describes as the exclusive Australian and New Zealand distributor of General Atomics’ PERSES technology, offered not to price the digestor at all. Instead it proposed a staged 20-year Build, Own, Operate and Transfer deal for a supercritical water oxidation plant at the Coffs Harbour Water Reclamation Plant. The report describes a process run at high temperature and pressure that uses water to oxidise the organic part of biosolids, including PFAS and other organic contaminants, leaving a mineral residue and a liquid sent back to the plant’s inlet (page 1496). PFAS are the persistent “forever chemicals”.

The proposal runs in four phases: a contract by 28 February 2027; interim haulage and off-site composting from March 2027; a first treatment train forecast for 2028/29 and a second for 2031/32; and handover to the City at the end of the term. The City’s biosolids would be tested at General Atomics’ demonstration plant in San Diego during the interim phase. Staff credit it with a potential long-term contaminant-management pathway, but note the technology has not been tested on the City’s biosolids, and planning approvals and firm pricing would not be available until testing and design are complete (page 1496). The rates it gave are described as indicative and non-binding (page 1496).

What staff recommend

For both biosolids contracts the recommendation was the same: decline to invite fresh tenders, because a new round is not expected to provide a timely or different market response, and authorise the General Manager to negotiate with contractors known to provide the services, under section 178 of the Local Government (General) Regulation 2021, with a further report to come back to councillors (pages 1495 and 1498). The reports say the two contracts depend on each other and propose that negotiations follow an approved probity plan (pages 1496, 1497 and 1499). No contract is awarded and no cost is put on either.

The City’s own long-range plan points the same way as the Ventia idea, at a bigger fix later. The Sewerage Services Development Servicing Plan, also on the 26 November agenda (item 15.13) and the subject of our story on the sewerage developer charge, says a central biosolids facility is to be built to manage sludge from all three plants (page 1443), and its capital works table lists $46,000,000 for biosolids thermal treatment at the Coffs Harbour plant in the 2030 column (Table 10, page 1481). That is years past March 2027.

Our view

This is the quiet item on a busy agenda that matters most to how a city of this size runs. Three contracts went out together; the organics one drew two bids and the two biosolids contracts drew, between them, an unpriced concept, a bid the City could not evaluate and nothing at all. That says the regional market for taking sewage solids is thin, and that the March 2027 date gives the City little bargaining room.

Negotiating directly is the sensible call when an open market has just answered with silence, and the regulation allows it. But councillors should not let the deadline choose a 20-year technology for them: the supercritical water oxidation offer is interesting precisely because it promises to deal with PFAS, and its own interim phase depends on haulage and composting off site, the very service nobody tendered for. The question residents are owed an answer to is a simple one: where do the biosolids from the three plants go in March 2027 if no negotiated contract is in place? Only the City can answer that. We asked the City of Coffs Harbour on 21 November 2026 and will add its answer here, or say if none arrives.

How we did this. On 21 November 2026 we read items 15.16, 15.17 and 15.18 of the business paper for the City of Coffs Harbour’s 26 November 2026 Ordinary Council meeting in full (pages 1493 to 1499), section 4.1 and Table 10 of the Sewerage Services Development Servicing Plan attached to item 15.13 (pages 1443 and 1481), and note E2-1 of the 2025/26 financial statements attached to item 15.1 (page 238). We could not read the confidential attachment to item 15.16. Companies are described as the reports describe them; Soilco and Australian Native Landscapes are named as tenderers only. The section headed Our view is opinion. We asked the City of Coffs Harbour on 21 November 2026 what happens to the biosolids if no contract is in place by March 2027.

On 27 November 2026 we read the minutes of the 26 November meeting for the resolutions on items 15.16 to 15.18 (see the note of 27 November).