The short answer. On 26 November the council adopted item 15.2 of the business paper for its Ordinary Council meeting, a staff recommendation with three parts: note the estimated cost of $27 million; consider allocating $9 million from the City’s Infrastructure Renewal Reserve in the 2028/29 Operational Plan; and lobby the state and federal governments for $9 million each. The vote was seven to one. The report is plain about the stakes: Without committed funding, the condition of the Jetty is likely to require closure to the public in the next 3-5 years.A

Exhibit A · from the source

The business paper's sentence warning that without committed funding the Jetty is likely to require closure to the public in the next 3-5 years
Page 302 of the business paper for the City of Coffs Harbour’s Ordinary Council Meeting of 26 November 2026, item 15.2, under the heading “Options”, read 20 November 2026. Outlined: the closure warning. The sentence after it recalls the 2024 resolution on the City’s role as Crown Land Manager. Open the item Back to the story

The proposed three-way split

City of Coffs HarbourInfrastructure Renewal Reserve, programmed for 2028/29, if councillors agree$9m
NSW GovernmentTo be lobbied for, not offered$9m
Australian GovernmentTo be lobbied for, not offered$9m
Estimated costBents 23 to 83, including a 15 per cent contingency$26.9m
City of Coffs Harbour, Ordinary Council Meeting 26 November 2026, item 15.2, recommendation (business paper page 299) and Issues and options (page 301). The report rounds the $26,918,433 estimate to about $27 million and divides it equally.

Why now

The Jetty has been here before. A geotechnical report attached to the item recounts its history: built from 1889 and finished in 1892 for timber, farm produce and coastal shipping, it lost its last commercial shipment in July 1979, was closed to the public in 1990 as it deteriorated, and reopened in October 1997 after a major reconstruction, with further pile and timber repair programs in 2007 and 2010 (pages 330 and 331). The staff report calls it the last surviving State Government-built jetty in NSW from the late nineteenth century (page 299).

That repair cycle is running out. A condition assessment above and below the water in 2023 and 2024, the same attachment says, concluded that the overall condition of the Jetty is poor and that the structure is approaching the end of its serviceable life. Most piles were rated fair to good, reflecting staged replacement, but more than 24 per cent of the girders were rated Condition 6 or worse, which it describes as severe deterioration and substantial loss of structural capacity, and termite activity was prevalent in the girders and corbels (page 331).

The money has been the problem. When councillors last looked at the Jetty, on 24 July 2025, they were told a Growing Regions Program application had failed and that $1 million (including GST) from the State’s Crown Reserve Improvement Fund would cover only the first four spans (page 299). Councillors endorsed a hybrid design and a revote of $237,962 to take it to detailed design and development consent (resolution 2025/168, page 300). The 2025/26 project budget, that grant plus the City’s share, is $1,142,450 excluding GST, still for part of four spans only (page 302). Previous attempts to secure substantial external funding have been unsuccessful, the report says; its case for asking again is that the design is now mature enough to give funders certainty about scope, cost and delivery (page 301).

What $26.9 million buys

The design, now at 50 per cent, keeps the existing 6 metre spans and the varied deck widths. What you can see stays timber: the raked outer piles, outer girders, bracing and decking. Inside, the piles, girders, capwales and corbels become fibre reinforced polymer (FRP) for durability and lower maintenance (page 300). It is built for a 50-year design life and a 22.5 tonne maintenance truck, enough for a 15 tonne fire truck, with a compliant balustrade (pages 300 and 301).

The cost estimate, Bents 23 to 83

ComponentAmount
Project planning (heritage, environmental review, development application, project management)$250,000
Establishment$450,000
Construction works (demolition, timber works, FRP works, fixtures)$21,607,333
Services (water, electrical, pedestrian lighting)$750,000
Completion, including third-party FRP certification$350,000
Subtotal$23,407,333
Contingency (15 per cent)$3,511,100
Total project estimate$26,918,433
Item 15.2, Financial impact (business paper page 302). Timber unit rates are 2018 rates adjusted by 16 per cent for CPI plus 2024/25 supplier advice; FRP rates are a supplier estimate. The report compares the total with $33 million for a timber-only structure and $23 million for the hybrid option reported in July 2025, adjusted for inflation.

The report lists matters still to be resolved in detailed design (page 301). Among them: buried historical harbour debris stopped drilling near two boreholes and is a significant risk to driving piles. Piles are expected to be 18 to 26 metres long, and beyond about 18 metres timber supply may run short, so steel piles may be needed in places, which may affect cost and heritage presentation. In a vessel impact, the uplift at one borehole (192 kN) exceeds the estimated tension resistance (118 kN) and needs more work. And the wave assessment relies on extrapolation beyond the available modelling. The report does not price these separately. A Heritage Impact Statement and Review of Environmental Factors come next, for development consent and approval under the Heritage Act.

If the money does not come

The report gives councillors three options: adopt the recommendation, amend it (for example by changing the City’s share or the split it asks for), or reject it (pages 301 and 302). It also recalls a 2024 resolution (2024/150) that, if funding is not forthcoming, councillors will get a further report on the City ceasing its role as Crown Land Manager for the reserve the Jetty sits on (page 302). In other words, the fallback on the table is handing the Jetty back to the State, not paying for all of it.

Our view

This is the strongest case the City has put for the Jetty: a 50 per cent design, a line-by-line estimate, and a clear ask timed for an election. An equal split is a fair opening position for a structure the report rightly treats as more than a local asset. Two things deserved a straight answer on 26 November, and the resolution as minuted settles neither. First, the City’s share is still something councillors resolved to consider for 2028/29, not a commitment now, while the closure warning runs three to five years; a funder will want to know the City means it. Second, the open risks on piles and debris are exactly the kind that move an estimate, and a 15 per cent contingency on an estimate that has already moved from the $23 million reported for the hybrid in July 2025 to $26.9 million leaves little room. Councillors should also be asking what happens if only one of the two governments says yes.

How we did this. On 20 November 2026 we read item 15.2 of the business paper for the 26 November Ordinary Council meeting in full (pages 299 to 303), and from its attachments the history and condition sections of the geotechnical assessment report (pages 330 and 331). We did not read the design drawings in detail. Figures are as the report gives them. We have not asked the City or either government about the funding request.

A related item on the same agenda, the sewerage developer charge, is in our story on the draft plan.

On 27 November 2026 we read the minutes of the 26 November meeting for the resolution and the vote (see the note of 27 November).