Updated 23 November 2026. The minutes are out. The unconfirmed minutes of the 19 November 2026 Ordinary Council meeting record that the council endorsed the planning proposal and resolved to forward it to the NSW Department of Planning, Housing and Infrastructure for a Gateway determination, eight votes to none (item 13.3, page 15). The resolution also delegates authority to the Director Community, Planning and Environment to make minor amendments to the proposal before it is submitted. The minutes do not say whether the reviewer’s note will come out. We will report what the Gateway determination says about public exhibition when the Department issues it.

Updated 20 November 2026. Councillors met on 19 November. The minutes are not yet published on the council’s meeting portal, so we do not yet know the decision; we will report it from the minutes. This story now puts the meeting in the past tense. Nothing else has changed.

The short answer

  • What councillors were asked to do: endorse a planning proposal that changes the zoning of the Lake Road land from C1 National Parks and Nature Reserves to C2 Environmental Conservation, and send it to the NSW Department of Planning, Housing and Infrastructure for a Gateway determination. That is item 13.3 on the 19 November agenda.
  • Why it matters: the council’s first-quarter progress report lists the Lake Road duplication, Ocean Drive to Chestnut Road, as off track, because the project cannot be lodged for approval until the land is rezoned, and that may run past 30 June 2027.
  • What it does not do: the report says the rezoning approves no road works and no clearing. National Parks has told the council no construction is allowed until the land is formally transferred, and that transfer has not happened.
  • The open question: whether anyone outside the council and two state agencies gets to comment. Officers say exhibition is for the Department to decide at Gateway.

The land, and how it left the reserve

The land is Lot 1 DP740499 and proposed Lot 1 DP1312900, on the southern side of Lake Road between Chestnut Road and Barton Crescent. The planning proposal describes it as irregular in shape, about 1.2 hectares, with about 450 metres of frontage to Lake Road. It adjoins what remains of the Lake Innes Nature Reserve.

Parliament took it out of the reserve. The National Parks and Wildlife Act now carries, in clause 58 of its Schedule 2, the revocation made by the National Parks and Heritage Legislation Amendment Act 2024: three parcels of Lake Innes Nature Reserve, of about 1.26, 0.36 and 4.59 hectares, identified in documents named PMHC_NPWS_REVO_002 to 004. Clause 63 vests the revoked land in the minister. Clause 64 then sets a condition on handing it on: The Minister must not transfer the land under Part 11 unless the Minister is satisfied appropriate compensation for the land has been provided.

The Act does not say which of the three parcels is the Lake Road land, and we have not seen the plans it refers to. On 15 August 2024 councillors resolved to progress the transfer of revoked land at four places: Lake Road between Ocean Drive and Chestnut Road, Lighthouse Road, and two stretches of Ocean Drive near Lake Cathie. The same resolution asked for a further report on the outcome of compensation discussions with National Parks. The council’s November register of outstanding resolutions says that report is expected in early 2027.

What the council’s own reports say about the road

Item 13.3 calls the rezoning administrative, and says more than once that it would not itself approve road construction, vegetation clearing or other works. Its executive summary also says why it is needed now: it seeks to remove an identified planning constraint to future works associated with the Lake Road Duplication Project. The attached planning proposal puts it more plainly. The land is to come to the council so that existing drainage pipes and open drains can sit inside the road reserve, and for the duplication of Lake Road and associated public infrastructure works.

A different item on the same agenda shows what is riding on it. The first-quarter progress report on the 2026-27 Operational Plan, item 13.5, lists five actions as off track, and the Lake Road duplication is the first of them.A Its detailed table says work on the environmental impact assessment is going ahead, and that the rezoning is a precursor to lodging the project’s environmental assessment.

Exhibit A · from the source

Port Macquarie-Hastings Council, Quarter 1 2026-27 Operational Plan progress report: the Lake Road duplication cannot be lodged for approval until land to be transferred from NSW National Parks and Wildlife Service is rezoned, which may extend beyond 30 June 2027.
Page 843 of the business paper for Port Macquarie-Hastings Council’s Ordinary Council Meeting of 19 November 2026, item 13.5 Quarter 1 2026-2027 Operational Plan Progress Report, under “Off Track Actions”, “Land tenure and external approvals”. Read 14 November 2026. Outlined: why the project is held up, and for how long it may be. Open the item Back to the story

The council’s 2025-26 annual report, item 13.4, says planning for the duplication is now the key priority on our local road network to manage congestion. It lists the duplication and the Ocean Drive and Lake Road intersection upgrade first among the projects the council will be seeking funding for, and its list of contracts over $150,000 for the year includes $299,746, excluding GST, to GeoLINK Consulting for the project’s environmental approvals. National Parks’ letter of 15 September 2026, attached to item 13.3, agrees the council can start rezoning before it owns the land, then adds: no construction works will be permitted on the Land until the land is formally transferred.

What is on the land

The planning proposal does not play down the site. It records that all of the proposed lot is in the council’s flood planning area, and all of it is either mapped coastal wetland or within the coastal wetland proximity area under the state’s Resilience and Hazards policy. Part of it falls under the Link Road Koala Plan of Management. It says the land holds native vegetation, and habitat for threatened species and ecological communities identified in earlier investigations for the duplication, and that it occurs within an area known to contain Koala habitat. It also lists mapped acid sulfate soils.

The proposal’s answer each time is that the rezoning itself disturbs nothing, and that any road works will need their own environmental assessment and approval. C2 is, the report says, the most appropriate conservation zone available for land no longer reserved under the National Parks and Wildlife Act, and the proposal notes that the site adjoins land already zoned C2.

Who gets a say, and when

The report says targeted consultation has been with council departments, National Parks and the Department. On the public, it says that public exhibition is not recommended at this stage, and that any exhibition requirement will be set by the Gateway determination. The planning proposal’s own timeline keeps a slot for it.

The planning proposal’s indicative timeline

  1. November 2026: consideration and decision by the council (the 19 November meeting).
  2. December 2026: Gateway determination by the Department.
  3. January to February 2027: agency consultation.
  4. March 2027: public exhibition, if required.
  5. April to May 2027: submissions considered, final proposal reported to the council and sent to the Department.
  6. June 2027: the amended local environmental plan is published.
Planning proposal, Part 6, Table 8 (pages 637 and 638 of the business paper). The dates are the council’s and are marked indicative. The progress report in Exhibit A says the rezoning may run past 30 June 2027.

One more thing in the attachment is worth knowing. The consultation section of the planning proposal, marked Version 2.0, October 2026, ends with a paragraph that reads like a reviewer’s note rather than part of the proposal:

I think that approach is more defensible at Gateway because it explains why C2 is the appropriate outcome without appearing to diminish the importance of community consultation.

Planning proposal, Part 5 “Community Consultation”, page 637 of the business paper for 19 November 2026, attachment 1 to item 13.3.

Our view

The rezoning itself is the right call. Land that is no longer a nature reserve cannot sensibly keep a zone written for nature reserves, and we agree with the report that C2 is the fitting replacement. The proposal says it adds no development potential, and nothing in it points to housing or any other use of the site.

But “administrative” undersells it. On the council’s own account this is the step the road it calls its key local priority is waiting on, on land that is coastal wetland, flood-prone and koala habitat, taken out of a nature reserve by an Act of Parliament in 2024. That is exactly the kind of change people who live along Lake Road and use the reserve would expect to see before it is final. The timeline already holds a March 2027 exhibition slot. Councillors could ask for it to be used rather than leaving it to Gateway, at the cost of a few weeks on a timetable the council itself says may already run past June 2027.

Two smaller things. The compensation the 2024 Act requires before any transfer is the figure that matters most to ratepayers, and the report on it is not due until early 2027, after councillors were asked to send the rezoning to the state. And the reviewer’s note should come out of the proposal before it goes to the Department. It changes nothing the proposal says, but a document that may be put before the public should read as the council’s case, not as notes on how that case will look.

Councillors met on 19 November; the minutes are not yet published. We will report what they decided from the minutes, and what the Gateway determination says about public exhibition when the Department issues it.

How we did this. We downloaded the full 1,154-page business paper for Port Macquarie-Hastings Council’s 19 November 2026 ordinary meeting from the council’s meeting portal and read item 13.3 with all four attachments (pages 595 to 645), the Lake Road entries in items 13.4 (the 2025-26 annual report) and 13.5 (the first-quarter progress report), and the register of outstanding resolutions in item 11.2. We read clauses 56 to 64 of Schedule 2 to the National Parks and Wildlife Act 1974 in the version in force from 10 June 2026 on the NSW legislation website. The Act gives three Lake Innes parcels; we have not seen the plans it names, so we cannot say which is the Lake Road land, and we have not added them together to compare with the 1.2 hectares. Page numbers are the business paper’s own. Councillors may amend, defer or reject the item on the day. We did not contact the council or National Parks for this story.