What was decided
On 23 September, in closed session, Armidale councillors resolved unanimously to
accept the tender from Bielby Holdings Pty Ltd, with a target budget of $319,345,296.50
exclusive of GST
. The same resolution caps what the general manager may commit under the
contract at the approved funding arrangements
. The NSW Minister for Roads and the
Minister for Recovery announced the award on 25 September, and the council published its
own release on 28 September.
Six bidders answered the council's call for expressions of interest in early 2025. Three
were shortlisted: the Seymour Whyte and SEE Civil joint venture, the CMC and McIlwain joint
venture, and Bielby Holdings. Tenders went to those three in November 2025, when the council
expected to name the winner in mid-2026. The draft minutes also record that the meeting was
reopened at 6.15pm that evening to clarify resolution 174/26
, the contract resolution,
without saying what was clarified. We will read the adopted minutes.
What the money buys, and what the figure is
The job is to restore the road to its condition before the disasters: the 2019 bushfires
and the 2020 and 2022 floods. The council's project background lists five elements:
upslope works for safety during construction, drainage and culverts designed for a 1 in 50
year storm, downslope repairs to restore the width of the road formation, pavement
rehabilitation, and scour repairs to bridge foundations. Disaster funding does not pay for
betterment
, so improvements at Big Hill, Flying Fox Cutting, Blackbird Flat and
other spots have come from the separate Fixing Local Roads and Fixing Country Roads
programs.
Three things about the $319 million are worth holding on to.
- It is a target budget for one contract, excluding GST. The ministers'
release calls it
the $319 million reconstruction
; the council's release says the contract will delivera significant component
of the reconstruction program, which also covers earlier emergency and immediate reconstruction works. - The program's total cost is not public. The council's background
paper says an early contractor estimate in 2024
significantly exceeded the funding approved to date
, so it paused the design-and-construct stage until more funding was assured. The project timeline records a revised funding approval in the last quarter of 2024. The council keeps its current total cost estimate confidential so as not to influence procurement. - The last published funding figure is older than that revision. As of September 2024 the council listed $427,965,929 in approved disaster recovery funding, excluding GST, across two declared disasters ($418,530,592 and $9,435,337). The money is Australian and NSW Government money under the Disaster Recovery Funding Arrangements, provided by the National Emergency Management Agency through the NSW Reconstruction Authority.
More may be asked for. The council's August status report says its consultant GHD has
assessed the damage from ex-Tropical Cyclone Alfred, ready for a further restoration funding
submission before the end of the year
.
What it means if you use the road
Kempsey-Armidale Road is the most direct route between the two towns, at 194 kilometres.
The council's figures put the Waterfall Way route at 251 kilometres and the Oxley Highway at
281, so 57 and 87 kilometres longer. The project site says the damaged section has been closed to
through traffic since 2022, and that it will remain closed until the main restoration
works are complete (due in late 2029, weather permitting)
. Counted from 2022, that is
about seven years.
For those allowed through, as at 5 October the project's road status page sets a 10 tonne limit, asks for loads of 10 to 20 tonnes to be registered at least 48 hours ahead, bars vehicles longer than 12.5 metres within the project boundaries, and asks drivers to call up on UHF channel 17.
The sequence, from the council and the project timeline:
- Coming months: site set-up and early works, including surveys,
compounds and environmental protection. The council says these are
expected to commence in the coming months
. - 2027: major construction
anticipated to begin
; the timeline puts the first detailed design package and the start of main works in the second quarter. The council expects more than 220 workers at peak construction. - Late 2029: completion,
weather permitting
.
The Kempsey end of the same road
The rebuild is in the Armidale Regional Council area; Kempsey Shire Council's own page
on it says so and refers inquiries to Armidale. On its own stretch, Kempsey Shire has a
separate job: soil nail walls at 14 landslip sites about 9 kilometres west of Bellbrook,
funded by Transport for NSW and built by PCA Ground Engineering, which started on 25 August
2025 and is scheduled to run through to November 2026. One council page for that work says
landslip repairs were expected to be finished by the end of September, with sealing by the
end of November, weather permitting. Its other page still lists the daytime closures as
running to the end of October. Neither page carries a date, so check with the council on
6566 3200 before you travel. Armidale's August report noted the Pee Dee closures were
causing construction fatigue and irritability
.
The Toose Road bridge, which we reported on 3 October, is a third project along this road: a new crossing of the Macleay from Kempsey-Armidale Road. The Armidale rebuild answers an older chain of disasters than the May 2025 flood behind the April package we set out in where the flood recovery sits. The council's list of declared disasters affecting the road includes that May 2025 flood too.
Our view: for people on the Macleay side, the number that matters is not $319 million, it is late 2029. Seven years with a main route shut to through traffic is a long time, and the published timeline is the right thing to hold the project to. On the money, the reason the council gave for keeping its total cost estimate confidential was procurement. With the main contract now let, the council should publish what the whole program is expected to cost against the funding approved. We will report the adopted minutes, the Alfred funding submission and the start of major works as they come.