The short answer. If you drive Rodeo Drive into Bowraville, the plan is
that you will not lose the crossing for the whole rebuild. Nambucca Valley Council’s
engineers say the new bridge will require the bridge to be closed to traffic for the
duration of the works due to the bridge deck level being lifted
, and they have costed a
temporary side track beside it at about $400,000. The council has allocated that money. Two
things still stand between the allocation and a side track: the council says it
will need to consult with and obtain any necessary approvals or agreement from the
relevant government agencies
first, and even with a side track there will be short
closures while the work is done.
What the council decided
Item 12.5 of the 23 September business paper, Bridge Betterment Program - Little
Motleys Bridge
, answered a request councillors made a month earlier. Its recommendation
passed unchanged as resolution 303/26, moved by Cr Angel and seconded by
Cr Jenvey: the council Allocates $400,000 from the Civil Works Reserve to fund the side
track to Little Motleys Bridge during reconstruction work
and will Return any unused
funds to the Civil Works Reserve.
Crs Angel, Ballangarry, Jenvey, Jones, Lee and MacSmith
voted for it and nobody voted against. Crs Simson and Vance had leave for the meeting and
Cr McWilliam is also listed under leave granted.
Before the item, Cr Jenvey declared a non-pecuniary, less significant conflict of
interest, recorded in the minutes as being because Cr Jenvey would be impacted from accessing
Bowraville if the bridge was closed
. Cr Jenvey voted on the item. The minutes are a draft until the council confirms them on 28 October.
From request to rebuild
- Feb and Mar 2022Severe weather and flooding that the betterment program responds to.
- 26 Aug 2026Councillors ask for a report on a bypass lane and its cost (resolution 244/26, 8 votes to 0).
- 15 Sep 2026Status note:
Meeting was held on site to discuss possible bypass options.
- 23 Sep 2026Up to $400,000 allocated for the side track (resolution 303/26, 6 votes to 0).
- Feb 2027The council’s estimated start of construction. Agency agreement needed before the side track proceeds.
What a side track buys, and what it does not
The report’s case is the detour. Closing the bridge would normally require
traffic to use an alternative route, resulting in a significant detour for the local
community and road users
, and the report adds that Given the current works being
undertaken at Macksville Bridge, the availability and practicality of alternative routes are
also reduced.
The side track would go on the northern side of the bridge, to allow
traffic to continue to cross the creek while the existing bridge is reconstructed
.
It is not a promise of uninterrupted access, and the report says so plainly.
The side track, in the report’s words
What it would do
avoid the need for the full detour for the majority of the bridge reconstruction
period and provide continued local connectivity while the works are undertaken
What it would not do
Access across the side track would still be temporarily disrupted to facilitate
activities such as concrete pouring, crane operations and approach road tie-ins
.
Who pays
On the report’s account, the $400,000 is a ceiling and a fallback. It says
Infrastructure Services will first seek to fund the works from savings within the Little
Motleys Bridge project and/or relevant program savings, including through the anticipated
reduced requirement to utilise project contingency.
The reserve money is there, it says,
to ensure the side track can proceed if sufficient savings are not identified within the
existing project and program budgets.
Its financial implications section says: There is expected to be additional costs associated with the project.
The order the money is meant to come from
- Savings inside the Little Motleys Bridge project, including any contingency it does not need.
- Savings elsewhere in the bridge program.
- If those fall short: up to $400,000 from the council’s Civil Works Reserve.
- Anything not spent goes back to the reserve.
The approval step matters because this is not only the council’s money. The report
calls the side track a change to the current project scope
and says agreement is
needed in relation to the proposed scope change, funding arrangements and any associated
regulatory or approval requirements.
Its risk table lists State Government Approval
Delay
as low likelihood, medium impact. The report does not name the agencies.
One of six bridges
Little Motleys is the only one of six crossings not yet under construction in what the council calls the
Betterment of Nambucca Valley Council River Crossings Program
, which replaces
ageing and vulnerable timber bridges with stronger, higher and more resilient
structures
. The council’s project page says the program is funded through the
jointly funded Australian and NSW Government Disaster Recovery Funding Arrangements and the
Regional Roads and Transport Recovery Package, with $9.98 million provided to Nambucca
Valley Council
, and that it follows the floods of February and March 2022. The new
bridges get stronger concrete structures, increased deck lengths, higher clearances over
waterways and improvements to the associated road approaches
. The report’s reason
for the full closure, a deck being lifted, fits that brief.
Six timber bridges, one still to start
The council’s list, as at 7 October 2026
Construction is now underway across five of the Betterment Bridges projects, with Little Motley Bridge progressing through construction planning with an estimated commencement date February 2027.The page does not say which five; it names six bridges and one exception, so the other five are marked under way. The page spells it “Little Motley”; the business papers say “Little Motleys”.
The page warns that road closure dates and construction programs are subject to
change due to weather, and unexpected construction issues
, so February 2027 is an
estimate, not a fixed date.
Why Bowraville asked
The request came from a notice of motion by Cr Jenvey at the 26 August meeting. The
motion did not argue against the rebuild. It opened: Building Back Better after flooding
to fix deteriorating and damaged bridge assets with disaster funding makes for good economic
management in a climate constrained world.
Its objection was to the closures stacking
up around one town.
enduring a second road closure along Rodeo Drive at Little Motleys Bridge, Bowraville for another four months, after the closure of Wirrimbi Road at Cassidy’s Bridge will have compounding impacts on the town of Bowraville.
The motion called that too lengthy a hardship for road-users going to Nambucca and too
much of an economic cost to businesses in Bowraville due to a lack of accessibility
, and
noted that because the bridge is not scheduled for a rebuild until February 2027, Council
has the time
to plan and cost a bypass. Eight councillors voted for the report and none
against. Four weeks later the side track was costed and the money allocated.
Our view
This is a council doing the obvious thing well and quickly: a request in August, an on-site look in mid-September, a costed option and a vote in the same month, and a funding order that tries the project’s own savings before the reserve. For a town already living with the closure at Cassidy’s Bridge, on the motion’s account, a crossing kept open for most of a rebuild is worth a lot more than its line in the budget.
What the papers leave out is what a Bowraville driver would most want to know: how long the bridge would be shut without the side track, how many days the side track itself would close for pours and crane lifts, and whether the agencies funding the program have agreed to the change. The report also does not give the bridge’s own budget, so readers cannot judge how likely it is that savings, rather than the reserve, cover the $400,000. Those are all answerable before February, and the useful next update from the council would answer them.
How we did this. We read item 12.5 of the 23 September 2026 business
paper end to end, the draft minutes of the same meeting, Cr Jenvey’s 26 August notice
of motion, and the council’s Betterment Bridge Projects page. Vote counts are from the
minutes. The $9.98 million is the project page’s figure for the whole six-bridge
program, not for this bridge. We have not seen a design, so we do not describe where the
side track runs beyond the report’s northern side of the bridge
.