The short answer. When the bypass opens, the old highway through
Coffs Harbour stays a state road, and the City has drawn what it wants that road to become:
a slower, greener street with more crossings, wider footpaths and a tree-planted median
through the city centre. It is a draft vision, not a funded project. The City’s
answer to When will the design be implemented?
begins: No timeline for implementation has been confirmed.
It adds that its plans fund detailed design of the first stage, but
at this stage, no funding has been identified for implementation works.
What residents could shape on exhibition was the direction, and the trade it makes between a
quicker drive and a better street. Submissions closed at 5pm on Monday 26 October.
What was on exhibition
The whole corridor, 10.2 km
Streetscape Design Guidelines for the former Pacific Highway from the Englands Road interchange to Korora Hill: tree planting, landscaping, materials, furnishings, public art, bike riding and entry statements at the three interchanges. A guide for future public works and for private development beside the road. The published estimate does not cover it.
The city centre, stage 1
A Detailed Concept Design from the Combine and Albany Street intersection to Coff Street, showing what the guidelines would look like on the ground, with a staging plan in three sub-stages and the concept estimate of $19.6 million excluding GST.
What the first stage would cost
The estimate is by quantity surveyors APLAS Group, working for the City’s design
consultants King + Campbell, and is dated 5 September 2026. It splits stage 1 into three
sub-stages and totals them at $19,604,436 excluding GST. It is frank about what that
number is: the design is at a highly conceptual masterplan design stage
,
and These estimates should therefore be considered Indicative Only
.
Stage 1, west to east, and its concept estimate
Construction cost excluding GST. Total $19,604,436.
Two things sit outside the figure. The surveyors were told to leave out a design
contingency, and say that at this level of design
we would recommend 5-10% allowance for Design Development Allowance be included within overall Development Budget
.
On their total that is about $1.0 million to $2.0 million more (our arithmetic). And the
estimate covers stage 1 only; it does not price the rest of the 10.2 kilometres.
What it would do to the drive
Transport for NSW commissioned Bitzios Consulting to test the city centre changes. The
changes modelled include cutting the posted limit from 50 to 40 km/h from Combine
Street to Coff Street, removing dedicated left-turn and slip lanes to build out kerbs at
crossings, closing Market and Little streets’ connection to the highway, adding a
right-turn lane into Harbour Drive, and new signalised pedestrian crossings at Combine,
Moonee and Coff streets. Both cases assume the bypass is open; in the report’s words,
These network changes as well as some optimisation of the traffic signals are the only differences between the Project Case and Base Case models.
Modelled travel time through the city centre, after the bypass opens
Pacific Highway, Combine Street to Coff Street, seconds. Without the changes, then with them.
| Year, peak, direction | Without | With | Extra |
|---|---|---|---|
| 2026 morning, northbound | 91 | 131 | 40 |
| 2026 morning, southbound | 120 | 156 | 36 |
| 2026 afternoon, northbound | 93 | 161 | 68 |
| 2026 afternoon, southbound | 86 | 182 | 96 |
| 2036 morning, northbound | 101 | 140 | 39 |
| 2036 morning, southbound | 125 | 151 | 26 |
| 2036 afternoon, northbound | 92 | 164 | 72 |
| 2036 afternoon, southbound | 97 | 155 | 58 |
The report’s own explanation is the speed limit:
travel times increase on the Pacific Highway due to the reduced speed limit.
It also finds traffic on the highway in the study area falls by about 20 per cent on
average as some drivers take other routes, spread across the network with no single route
greatly increasing, and that intersection results stay within acceptable performance
measures. The City’s summary of the same work is shorter:
While some increases in travel times are expected as vehicle speeds are reduced, the overall impacts are generally minor, as traffic is redistributed across the wider network.
On the table above, the largest modelled change is the 2026 afternoon southbound trip: 86 seconds becomes 182, an extra 96 seconds, a little more than double (our arithmetic). The smallest is 26 seconds, southbound in the 2036 morning peak.
Parking, the slip lane and the trees
The City says parking surveys in November 2023 found on-street parking along the corridor
significantly underutilised (in some instances utilisation is less than 50%)
,
partly because many spaces are not line marked. In the city centre section it counts about
100 spaces that would fit if marked; the concept keeps about 86 and removes about 14 for
wider footpaths, trees and crossings. The City’s view is that, because the spaces are
unmarked and not fully used, this would not be a noticeable loss.
About 100 spaces in the city centre section
Each square is one space. Grey: kept, about 86. Coral: removed, about 14.
The concept removes the dedicated left-turn slip lane at the Coff Street intersection.
The City says that makes room for footpaths, landscaping and public space, and for a safer,
more direct connection to a separated on-road bicycle path on the eastern side of the highway from Coff Street to Orlando Street,
linking the city centre to Park Beach Plaza. Within the city centre itself the guide does
not propose separated bike paths; riders would share a slower street. The April design
workshops pointed the same way: at both, the dot votes went to the stage 1 layout called
Maximise parking and tree planting
(19 at the staff workshop, 44 at the committee workshop) and none to the layout with a
two-way cycleway. For the median, the City has
shortlisted three trees and is asking which residents prefer: Leopard Tree, Brushbox and
Tallowwood.
Who decides, and who pays
The City prepared the guide with Transport for NSW, but the road is not the City’s.
The former Pacific Highway corridor will remain under the ownership, management and control of Transport for NSW.
Any change inside the corridor needs Transport for NSW approval, and the project page says
Any initiatives identified in the guide will be subject to further design, funding, approvals and collaboration with Transport for NSW.
How the guide got here, and what comes next
- 28 Sep 2023Council endorses the Coffs Harbour Movement and Place Strategy, with an action to develop a City Spine Renewal Strategy.
- 27 Nov 2025Council endorses the Post Bypass Renewal Action Plan, naming streetscape guidelines and a detailed concept design as priority actions.
- 15 and 16 Apr 2026Two design workshops: City and Transport for NSW staff, then councillors, members of three council committees and other stakeholders.
- 9 Jul 2026Traffic modelling report for Transport for NSW, version 002.
- 5 Sep 2026Concept design estimate for stage 1.
- 24 Sep 2026Council votes, with no councillor asking to speak, to exhibit the guide and to work with Transport for NSW on a lower speed limit and Harbour Drive upgrades.
- 25 Sep 2026Exhibition opens.
- 13 to 15 OctPop-ups in City Square, 9.30am to 2.30pm each day.
- Mon 26 OctSurvey and submissions closed, 5pm.
- No dateFinal guide to Council for consideration of endorsement. No implementation timeline, and no implementation funding identified.
To have a say: the survey and the submission form are on the project page, and postcards can be returned to Yarrila Place (Level 1), Harry Bailey Memorial Library, Toormina Library or Woolgoolga Library. Submissions will be published on the City’s website; the City says your name and suburb may be shown, but not your contact details.
What the council paper adds
The report that put the guide on exhibition, item 15.2 of the City’s
24 September 2026 council meeting, says the design work is
paid for. The action plan’s first initiative, the guidelines and the concept design,
was funded by a $100,000 grant from the NSW Government
, which the report elsewhere says came
from Transport for NSW, and
$50,000 each from two council committees, the Highway Bypass Integration Committee and the
City Centre Masterplan Committee. Building it is another matter. The report puts the
preliminary capital cost of stage 1 at $19,604,436.09, the surveyors’ figure to the dollar,
though it does not say whether that excludes GST, and says
While the project is currently unfunded, the City will actively seek Australian and State Government grant funding once the design is adopted.
On the report’s own timing, the lower speed limit may not wait for the guide. Council resolved to note that the City
will collaborate with Transport for NSW to reduce the speed limit for the bypassed section of the former Pacific Highway in alignment with the design guide
,
and to make initial or temporary upgrades at the Harbour Drive intersection. The report
gives the timing it wants: Implementing these changes concurrently with the bypass opening
would help drivers adjust, it says. The limit is Transport for NSW’s to set, and neither
the report nor the resolution names a figure or a date; the modelling above tested
40 km/h through the city centre. The report also says the City and Transport for NSW
will look at temporary activation and demonstration projects
in the corridor once the bypass opens.
Transport for NSW’s letter of 14 September, attached to the report, supports
putting the designs on exhibition, refers to a memorandum of understanding with the City,
and says the agency will take the project to its Strategy, Planning and Products Committee
for noting
. It is a letter of support for the exhibition, not an approval,
and does not mention money. The resolution itself records that the agency’s approval of the guide
is required as the road manager
.
The report also lists what the City and its bypass committee are still asking the
Australian and NSW governments for: entry gateway statements for the city centre,
intersection upgrades along the 10.2 kilometres once the bypass is open, better signage,
and Dangerous goods to travel through the tunnels on the new Pacific Highway bypass of Coffs Harbour
.
No councillor asked to speak on the exhibition. Item 15.2 was one of 14 items adopted
together by exception, as no Councillor has indicated a desire to speak to them
,
and the minutes record it CARRIED UNANIMOUSLY BY EXCEPTION
; the
motion to take those items together passed 7 votes to none.
What the action plan adds
The guide comes out of the Post Bypass Renewal Action Plan, which Council endorsed on
27 November 2025: 11 initiatives, prepared by City staff with Transport for NSW and the two
committees, published as attachment 1 to item CPC25/50 of that meeting’s
agenda. Its stage 1
runs from McLean Street to Coffs Street
.
The exhibited concept design and its estimate start further west, at the Combine and Albany
Street intersection; on our reading of the staging plan, sub-stage 1B, $4,506,369 of the
estimate, is the stretch between that intersection and McLean Street.
The plan also lists the separated bike path that the guide does not propose within the city centre. Its
Initiative 7 is a detailed design for a bike path along the whole bypassed highway,
Physically separated from both motor vehicle traffic and pedestrians
,
listed for 2028 onwards. The plan’s timetable had the Harbour Drive intersection
upgrade and the city centre gateway statements delivered in 2027/28, and adds that
Timing and delivery of initiatives is indicative only and is subject to resources and funding.
For money it lists grant programs the City could apply to, among them Transport for
NSW’s Your High Street and Get NSW Active programs and the Australian
Government’s Active Transport Fund.
Council endorsed the plan unanimously in November and asked for more than its officers’
formal recommendation. The minutes add two points: to seek NSW Government funding in the short
term for the plan’s business bypass readiness program,
to recognise the need of the business bypass readiness program now
,
and to ask Transport for NSW for $50,000 towards the north and south entry statements,
Initiative 6.
Our view
This is the plan our bypass coverage said to watch for: the point where the question stops being engineering and becomes what Coffs does with its main street, the question every town bypassed earlier in the upgrade has faced. The guide’s direction matches what it quotes from Transport for NSW’s own design manual for an arterial high street: wider footpaths, street trees, lower speed limits, places to stop. In our view a greener, slower centre with more crossings is a reasonable bet for a city that is about to lose its through traffic.
Two things deserve plainer words than the consultation gives them. First, the trade.
The City calls the overall impacts generally minor
, which is a fair summary of the network, where traffic thins and
spreads out. It is not how the change will feel to someone driving south through the centre
at the afternoon peak, whose modelled trip goes from under a minute and a half to just over
three minutes. That may well be worth it; a high street is meant to be slower. But residents
should be told the number and asked whether it is, not told it is minor. Second, the money.
The guide prices one stage at about $19.6 million before GST and before the design allowance
its own surveyors recommend, the road belongs to Transport for NSW, and the City says no
funding has been identified for the works. Endorsing the guide will not build it. The useful
thing a submission can do is say which pieces matter most: the City says feedback will help
identify which projects and initiatives are most important to the community.
How we did this. On 8 October 2026 we read the City’s Have Your Say project page and its FAQs in a browser, and downloaded and read five of the eight published documents: the 24-page draft guide, Appendix 3 (the staging plan), the 8-page concept estimate summary, the 157-page traffic modelling report (sections 1 to 5) and the 14-page design workshop report. We did not read Appendix 1 (streetscape guidelines), Appendix 2 (the detailed concept design, 45.4 MB) or Appendix 4 (median tree options), so we describe the concept design only as the City’s FAQs and the modelling report describe it. The sub-stage extents are read off the staging plan’s map, which has no written description. The estimate summary gives sub-stage totals only; its detailed breakdown was not published with it. Percentages and differences are ours, computed from the published figures. The modelled travel times are for the stretch of highway between Combine Street and Coff Street that the report models.
Updated 17 October 2026. We read the council report on the exhibition (item 15.2, 24 September 2026), its Transport for NSW letter, and the meeting’s minutes on the City’s meetings portal in a browser. We still have not read the Post Bypass Renewal Action Plan itself, which Council endorsed on 27 November 2025 (resolution 2025/246, as the September report records it). Papers from that meeting sit on the City’s earlier meetings platform, which did not answer from our network on 17 October, and we did not find the plan on the City’s website or the Have Your Say page. The initiative wording quoted in the September report is the only part of the plan we have seen. (The papers are also on the City’s current meetings portal, and we have since read the plan: see the note of 20 October.)
Corrected 20 October 2026. The note above said the November 2025 papers sit on the City’s earlier meetings platform, which did not answer from our network. They are also on the meetings portal we read on 17 October, in its list of previous meetings; we did not look back that far, so we missed the plan. We have not checked the earlier platform again. The action plan is attachment 1 to item CPC25/50 (agenda pages 439 to 462). On 20 October we read the report, the plan and the minutes, which record resolution 2025/246, and added the section headed What the action plan adds. Nothing else in the story changed.
We will read the report that brings the final guide back to council and set out what changed after exhibition, and any funding attached to it.